Construction Update - 1 Lacey
Construction has commenced at 1 Lacey in Surry Hills, here is the latest news.
Construction works at No 1 Lacey are generally progressing as programmed with the current forecast date for practical completion being October 2017.
Activities that lie on the critical path to completion are on program with concrete works associated with the new lift and stair core completed and the erection of structural steel to the roof and subsequent installation of the roof sheeting due for completion early in March.
Fitout works to the residential apartments are lagging behind program, but are expected to accelerate in order to mitigate any potential delay to the date of practical completion.
Restoration and remediation works to the Kippax Street and Lacey Street facades is generally complete with the focus now on the southern courtyard facade remediation, restoration and erection of steel walkways.